5.2. Prepare a Testday

Before you drive to the test track and execute your test day you should prepare and ensure the following:

5.2.1. Prepare Hardware

  1. Install the DV System as it will used on the Testday: Installed DV Box, installed Tractive System Accumulator, installed actuators including autonomous system brake, installed shutdown unit without bridging any shutdown circuit participants.

  2. Ensure that one can drive manually with installed DV system.

  3. Ensure that the inspection mission is running successfully and the RES works as expected.

  4. Ensure that the ACU can record camera images.

5.2.2. Prepare Software

  1. Ensure that the Autonomous System runs with the version(s) that should be tested. (not necessary on the ACU) (see Software Testing)

  2. Ensure that the Autonomous System on the ACU is up to date.

  3. Ensure that the control and inference module are still working on the ACU, fix the issues otherwise.

5.2.3. Prepare Materials

  1. Ensure that you packed everything you need generally/mechanically

    Table 5.1 General/Mechanic Items

    Item

    Quantity

    Normal storage location

    Vehicle

    1

    CUBE

    Nose

    1

    CUBE

    scuba tank, pressureized 200 bar

    1

    Diving Shop

    Toolbox

    1

    Lars Peters or CUBE

    Troque wrench including nut

    1

    CUBE

    Splints for wheel nuts

    4

    CUBE

    Quick Jack

    1

    CUBE

    Fire extinguisher

    2

    CUBE

    Ratchet straps

    2-3

    CUBE

    Undertray

    1

    CUBE

    Airpump for EBS

    1

    tbd

    Scuba tank adapter

    1

    tbd

    Duct Tape

    1

    CUBE

    Power strip

    1

    tbd

    Cable drum (not italian)

    3

    tbd

    Table 5.2 Electrical Items

    Item

    Quantity

    Normal storage location

    STM32 Debugger

    1

    E-Wagen, top drawer

    CAN Interface with respective conncetion cables

    1

    E-Wagen, top drawer

    Master Switches

    3

    E-Wagen, top drawer

    Multimeter

    1

    E-Wagen, some drawer

    Measuring tips for Multimeter

    1 pair

    E-Wagen, some drawer

    Power supply for charging LV

    1

    E-Raum, somewhere

    USB extension cable, 3m

    1

    tbd

    RES

    1

    tbd

    RES accumulator

    2

    tbd

    RES power supply

    1

    tbd

    DV Box

    1

    AS Room, somewhere in cabinet

    Cable ties

    1

    CUBE

    Electrical tape

    1

    E-Raum

    Table 5.3 Items for Autonomous System

    Item

    Quantity

    Normal storage location

    50m Tape Measure

    2-3

    Tool cabinet 8

    Screen with power supply and HDMI cable

    1

    AS Room, AS box

    Keyboard

    1

    tbd

    Mouse

    1

    tbd

    50 Ethernet cable drum

    1

    AS Room, top of cabinet

    Ethernet cable

    atleast 2

    tbd

    Zed camera cable

    1

    tbd

    Drone

    1

    Media AG Eppelheim

    Chalk

    1 package

    tbd